Venezuela

Diagnosis and Improvement of Gas System in the Northeast

Project: Diagnosis and Improvement of Gas System.

Client: Empresas filiales de PDVSA.

Scope of Work: Engineering for the maintenance, adjustment, cleaning and startup of the main line to the gas flow station. Diagnosis and identification of the operational problems of the gas supply to the electrical plant. Solutions, opportunities for improvements, adjustments and recommendations for the correct operation of the plant without affecting the model and increasing production of the Flow Station as a part of the installation of three vertical vessels and two condensate boots.
 

"Josefa Camejo" Thermoelectric Generation Plant in (West)

Project: EPC Thermal Power Generation Plant in the West.

Client: Corporación Eléctrica Nacional – CORPOELEC.

Scope of Work: Engineering, Procurement and Construction Project, developed in an area of 32 hectares, which includes the supply, transport, installation and commissioning of three generation turbines of 150 MW each (on site), simple cycle and system of dual fuel. It has the possibility of future installation of a combined cycle, expanding the installed capacity of the plant.

The Plant Balance (TPB) covered the storage and treatment systems for liquid fuel, compression and treatment of gas, service air and instruments, potable water. Also demineralized water systems, collection and treatment of effluents, control and telecommunications, as well as service buildings, control room, administrative buildings, warehouse and maintenance workshop.

It also included the training of the personnel responsible for the operation and maintenance of the plant.

Installed capacity:  450 MW.

Impact: Contribution to Sistema Interconectado Nacional (SIN), Complejo Refinador Paraguaná (900 thousand barrels per day), Zona Franca and communities of Falcón, Venezuela.

Thermoelectric Generation Plant "Alberto Lovera" in the East (North)

Project: EPC Thermal Power Generation Plant in the Northeast.

Client: Petróleos de Venezuela S.A. – PDVSA.

Scope of Work: Engineering, Procurement and Construction Project, developed in an area of 6 hectares, which includes the supply, transportation, installation and start-up of two 150 MW generation turbines (on site), single cycle and power generation system. dual fuel. It has the possibility of future installation of a combined cycle, expanding the installed capacity of the plant.

The Plant Balance (TPB) covers the systems of storage and treatment of liquid fuel, compression and treatment of gas, service air and instruments, drinking water, demineralized water, collection and treatment of effluents, control, telecommunications and service buildings, control room, administrative buildings, warehouse and maintenance workshop. It also includes the training of the personnel responsible for the operation and maintenance of the plant.

Installed capacity: 300 MW.

Impact: Contribution to Sistema Interconectado Nacional (SIN), Refinería Puerto La Cruz (187 thousand barrels per day) production of oil and gas in northern Anzoátegui and communities of the state.
 

 

Thermoelectric Generation Plant "San Diego de Cabrutica" in Oriente (South)

Project:  EPC Thermal Power Generation Plant in the Southeast.

Client: Petróleos de Venezuela S.A. – PDVSA.

Scope: Engineering, Procurement and Construction Project, developed in an area of 20 hectares, which includes the supply, transport, installation and start-up of two 150 MW generation turbines (on site), single cycle and gas fuel. It has the possibility of future installation of a combined cycle, expanding the installed capacity of the plant.

The Plant Balance (TPB) covers gas treatment systems, service air and instruments, drinking water, collection and treatment of effluents, control room, telecommunications, as well as service buildings, control room, administrative buildings, warehouse and maintenance workshop, as well as a residential camp for the fixed personnel of operation and maintenance of the plant. It also includes the training of the personnel responsible for the operation and maintenance of the plant.

Installed capacity: 300 MW.

Impact: Contribution to Sistema Interconectado Nacional (SIN), Faja Petrolífera del Orinoco (800 thousand barrels per day refining), Zona Franca and communities of Anzoátegui, Venezuela.
 

 

Thermoelectric Generation Plant "Ezequiel Zamora" in the Center

Project: EPC Thermal Power Generation Plant in Central.

Client: Petróleos de Venezuela S.A. – PDVSA.

Scope of Work: Engineering, Procurement and Construction Project, developed in an area of 12 hectares and in two stages. The first includes the supply, transport, installation and start-up of a 150 MW generation turbine (on site), simple cycle and gas fuel. The second stage includes a 170 MW generation turbine (on site), simple cycle and gas fuel. It has the possibility of future installation of a combined cycle, expanding the installed capacity of the plant.

The overall Plant Balance (TPB) is made up of gas compression and treatment systems, service air and instruments, drinking water, effluent collection and treatment, control room, telecommunications, in addition to service buildings, control, administrative buildings, warehouse and maintenance workshop. It also includes the training of the personnel responsible for the operation and maintenance of the plant.

Installed capacity: 320 MW.

Impact: Contribution to Sistema Interconectado Nacional (SIN), production of non-associated gas, gas compression facilities and communities of Guárico.
 

 

Hotel & Spa IKIN (Isla of Margarita)

Project: "Adaptation of the Electricity and water service system / Hotel & Spa IKIN / Finishing project and services".

Scope:

  • Detail Engineering for the Adaptation of the Electric System and the Service Water System of the Ikin Hotel & Spa
  • Partial supply of equipment and materials to be used in electrical installations
  • Inspection service of civil and electrical works, to ensure the adequate technical execution of the project
  • Adaptation of the Telecommunications System

General activities:

  • Selection and Purchase of equipment
  • Start-up of the new "Cubagua" Room Module
  • Start-up of a new Administrative Building
  • Adaptation of the Telecommunications System
  • Construction of pipelines for the adaptation of the Telecommunications System
  • Purification of service water

Achievements:

With the work in development you will get:

  • Increase in capacity (32%) of accommodation with 24 new rooms and a suite of 500 m2
  • Independence in the purchase of drinking water and ice
  • Improvement in the Telecommunications System (voice, data, tv, cctv and telephony)
  • 100% backup of the electrical capacity, with an autonomy of 6 continuous days
  • Improvements in all administrative and operational services of the hotel
  • All facilities are left for future expansion (construction of Spa, Bar and new Pool)
  • Improvement of laundry services, storage of refrigerated food and pastry
  • Installed capacity: 79 rooms, including 3 suites
  • Impact: Raise the quality of services at the Ikin Hotel & Spa

Contact

Main Offices, Caracas

Av. Francisco de Miranda, Centro Empresarial Galipán,Torre C, Piso 7. Caracas – Venezuela.
Phones: +58-212- 901.36.11 / 901.37.00 al 04.
Fax: +58-212-901.36.11
Email for information and Business is: This email address is being protected from spambots. You need JavaScript enabled to view it.
 
Email for Human Resources is: This email address is being protected from spambots. You need JavaScript enabled to view it.

Indigo Energy International, C.A.
RIF. J - 29500043 - 0
All rights reserved 2015.

      

We use cookies to improve our website. By continuing to use this website, you are giving consent to cookies being used. More details…